Skip Navigation and go to Main Content
JCC Home page JCC Home Page
Home » Departments & Services » General Services » Capital Projects - Firestation 4
  Facebook Twitter YouTube Calendar
  Click to change text size Print this page ePayment Share this page

Contact Information:

 

General Services

113 Tewning Rd.
Williamsburg, VA 23188

Directions - Directory

 

P: 757-259-4080
F: 757-258-1528

 

general.services@
jamescitycountyva.gov

 

Hours of Operation

 

7:30 - 4:30 p.m.
Monday-Friday

 

Project:

 

Firestation 4

Aug. 20, 2014

Scope of Work

James City County Fire Station 4 was originally built around 1980 and is in need of replacement. The new building will be approximately 14,400 square feet with a 3 vehicle bay facility, living quarters for up to 12 individuals, offices and space for training and storage. It was determined that an expansion of the site with fire operations taking place in the existing building while the new building is constructed on an expanded site footprint would provide the most cost effective solution. This subsequently required purchase of an adjoining property to accommodate the larger building and site restraints necessitated plans for retrofit of an offsite stormwater facility to treat stormwater from the expanded fire station impervious area. This project is intended to be constructed for LEED Silver certification.

Status of Project

The project is currently under construction. Work started in November 2013 with the retrofit of the offsite BMP in the Westmoreland Subdivision. The offsite work was completed in December 2013 despite frequent rains and poor drying conditions. Site work began with clearing of the fire station site in December 2013 with site improvements beginning in January 2014. Site work has been hampered by poor weather but, the contractor has made progress with the stormwater piping, utility relocation and preparation of the building pad. Footings were poured in March and the foundation and concrete masonry unit (CMU) walls began in earnest in May. May also saw the all utility relocation complete. The CMU walls and roof trusses were completed in mid-August. Roof decking is going on and the building should be ‘dried in’ with mechanical rough in complete in Mid-September.

July 8, 2014 - site conditions
Final Slab Pour
Site Conditions June 2, 2014
Footing Work
Offsite BMP Complete
Site Conditions April 5, 2014
Site Conditions March 14, 2014
Stonehouse
Future Fire Station 4 Front Building Elevations
Construction Site 021214

Click pictures
for larger views.

Schedule

Construction Phase - 36 percent complete

Budget

$4.1 M Approved

HVC Chennault Architectural Corp - $313,693
Contract Amount and percent completed - $257,464 – 82.1 percent
AES Consulting Engineers - $58,181
Contract Amount and percent completed - $57,017 – 98 percent
AR Chesson Construction Contract - $3,279,000
Contract amount and percent completed - $1,127,294 – 36 percent
Additional Services  -  $226,544

 

Milestones

  • Property acquisition.
  • Site plan approval
  • Bids complete
  • Construction underway
  • Offsite BMP work complete
  • Footings complete
  • Utility relocation complete
  • Storm sewer substantially complete
  • Slab poured with plumbing and electrical underslab work complete
  • CMU Installation Complete

 

Next Steps

  • Complete brick masonry
  • Install roof decking
  • Install mechanical rough in
  • Dry-in the building

 

Project Issues

  • Wet, snowy winter
  • Slow utility relocation
  • Frequent summer rains

 

Return to Projects page >>

The Official Site of James City County, Virginia
e-Subscribe | Contact Us | How do I? | e-Payment
Privacy Practices and Security Policy

James City Government Center · 101 Mounts Bay Road · Williamsburg, VA 23185