James City County Library

Stormwater BMP Retrofit Project - December 2017

Scope of Work

This project consists of the enhancement of an existing stormwater management facility and the construction of new bioretention facility at the library. The existing facility will be retrofit so that it provides a higher level of water quality treatment and also reduces its maintenance costs. The new bioretention facility will treat portions of the library property that currently has no stormwater facility.

Quick Links

Schedule

  • Civil Engineering Design: Complete - 100%
  • Construction Phase: Began April 17, 2017
  • Substantial Completion: June 30, 2017

Budget

  • Estimated Budget - $230,000
  • David A. Nice Builders, Inc. - $208,617.59
  • Contract amount and percent complete - $208,617.59 - 100%

Milestones

  • Site plan approved Oct. 21, 2016
  • Construction contract awarded Feb. 14, 2017
  • Beginning of construction April 17, 2017
  • Clearing complete May 8, 2017
  • Work complete June 30, 2017

Next Steps

  • All work complete and accepted

Project Issues

  • N/A