Scope of Work

The project will repair dilapidated stormwater structures on Deere Circle along with installation of new in-channel structures to stabilize the banks and provide energy dissipation of the stormwater flow. The banks will be re-graded, stabilized and planted with native riparian plantings.

Status of Project

The project is substantially complete.

Schedule

  • Complete Final Design - Completed
  • Advertisement for Bids - January 2018
  • Initiation of Construction - March 2018
  • Project Completion - May 2018

Budget

  • Professional Services - $45,000
  • Construction - $124,000

Milestones

  • 100% Design completed
  • Submitted to James City County Community Development Department and Stormwater & Resource Protection Division
  • Design approved
  • Project Advertised
  • Contractor selected:  Environmental Quality Resources
  • Notice to Proceed Issued
  • Construction begins
  • Substantial completion

Next Steps

  • Punch list items completed
  • Submission of As-Built Drawings

Project Issues

  • None