US 60 Bike, Pedestrian & Safety Improvement

Drainage and Roadway Improvements – Oct 2022


Scope of Work

This project involves bicycle, pedestrian and drainage improvements on Richmond Road beginning at Forge Road and ending just before Toano Middle School for a total length of 0.48 miles. Improvements include the addition of a landscaped median with pedestrian refuges, sidewalk and ADA ramp improvements, crosswalks, striped bike lanes on each side of the road, and storm drainage improvements. The project addresses inadequate drainage (PDF) by the installation of a parallel drainage system and additional inlets to drain existing isolated low points. Virginia Department of Transportation (VDOT) Revenue Sharing funds will be received in July 2018 to help fund the project.

Stormwater and Streetscape Improvements Map

Schedule

  • Complete Engineering Design – January 2022
  • Bid Project – June 2022
  • Initiate Construction – Fall 2022
  • Project Completion – Fall 2023

Budget

  • Estimated Budget - $1,659,391 Fall 2018
  • Budget Estimate update - $1,699,398 June 2021
  • Budget Estimate update - $2,199,832 – Sept 2021
  • A. Morton Thomas and Associates, Inc. (final design contract) - $99,656
  • Contract payments and percent completed (final design contract) - $93,231 - 94%
  • Right of Way – Timmons - $12,029 – 100%

Milestones

  • Received authorization to advertise project from VDOT
  • Acquired Easements
  • Acquired Authorization from VDOT to Award contract
  • Henry S. Branscome, LLC low bid at $2,172,186

Next Steps

  • Award contract at October 25th BOS meeting
  • Construction

Project Issues