Grove Area Stormwater & Roadway Improvements

Drainage and Roadway Improvements - July 2022

Scope of Work

This project proposes to widen existing travel lanes to the minimum standard for sections of the road network within the Grove residential neighborhood and to address historic drainage and flooding issues in the area. The project addresses deficient pavement width through the addition of new asphalt pavement and alleviates roadway drainage issues by reestablishing ditch grades and driveway culverts. In addition, new storm drain pipes will be installed to increase flow capacity under roads and to connect ditches that do not have an existing outfall or are very poorly drained. Virginia Department of Transportation (VDOT) Revenue Sharing funds have been applied for to help fund the project.

Schedule

  • Complete Engineering Design – Fall 2022
  • Utility Relocation/Easement Acquisition – Spring/Summer 2023
  • Advertise Project – Fall 2023
  • Initiate Construction – Winter 2023
  • Project Completion – Summer 2024

Budget

  • Estimated Budget - $1,173,700
  • New Estimate (May 2020) based on increased scope of Project - $1,801,600
  • New Estimate (Oct 2020) based on increased scope of Project - $1,909,000
  • New Estimate (Oct 2021) based on increased scope and materials cost - $2,420,000
  • Draper Aden Associates - $123,900
  • Contract payments and percent completed - $97,732 – 79%

Milestones

  • 90% Submittal complete Oct 2021 – in review by County and VDOT

Next Steps

  • Final Plan revision and submission
  • Obtain required drainage easements

Project Issues

  • Need to acquire permanent easements for work on private property.
  • Multiple utility relocations will be required.
  • Increased project scope has increased project costs.