Recreation Center

Hospital Space Renovation - January 2020

Scope of Work

Renovate the current cardio-room and the space previously occupied by Sentara at the James City County Recreation Center to accommodate a new stretching area, a personal training room, a yoga studio, and a newly relocated and expanded cardio-room.  

Status of Project

  • Completed

Schedule

  • Complete Final Design - December 2018
  • Advertisement for Bids - December 2018
  • Board Approval - February 2019
  • Initiation of Construction - March 2019
  • Project Completion - January 2020

Budget

  • Professional Services - $33,000
  • Construction - $250,000
  • 9 New Windows - $57,412

Milestones

  • Initial Recreation Center patron input
  • Conceptual drawing by RRMM
  • Complete set of A&E drawings
  • Demolition complete of the space
  • Sheetrock installed
  • Electrical conduits installed
  • TRX Beams installed
  • Installation of the lights

Next Steps

  • New work of the space
  • Replace windows scheduled for the middle of October
  • Paint and finishes

Projects Issues

  • Windows have been leaking at the sills
  • Getting pricing to replace
  • Have awarded the bid to replace 9 windows in the new space