Jolly Pond Road

Turnaround Project - May 2020

Scope of Work

Design and construct turnarounds at either termini on Jolly Pond Road. The project is required to provide for the safety of the travelling public. The James City County Board of Supervisors approved the abandonment of a section of Jolly Pond Road where it crosses over the dam due to safety concerns. The turnarounds will provide a safe location for traffic to turn around.

Schedule

  • January 2020 – Begin scoping and design of project
  • May 2020 – Complete Concept Plan
  • June 2020 – Revise Concept Plan based on comments
  • July 2020 – Submit 90% Right-of-Way Plan
  • August 2020 – Revise 90% Right-of-Way Plans
  • September 2020 – Complete Plats for Right-of-Way Acquisition
  • October 2020 – 100% Construction Plans Submitted
  • November 2020 – Plan Approval from VDOT/JCC
  • December 2020 – Advertise Project
  • January 2021 – Bid Opening
  • February 2021 – Begin Construction
  • March 2021 – End Construction

Budget

  • Estimated Budget - $145,000

Milestones

  • December 2019 - BOS approves abandonment of section of Jolly Pond Road.
  • May 2020 – County has received Concept Plan and is reviewing

Next Steps

  • Begin survey and concept design of turnarounds
  • Design of accepted concept plan

Project Issues

  • None