Jamestown Beach Event Park Paving Project

Existing Road and Parking Area Improvements - July 2021 

Scope of Work

Perform maintenance to existing roadways and parking areas by filling potholes and degraded road surfaces and installation of new asphalt on roadways that service the park. Enhance accessibility to parking areas in accordance with the Americans with Disabilities Act.

Jamestown Beach Event Park Paving Project

Schedule

  • Design completed – July 2021
  • Advertise project – Aug. 2021
  • Seek BOS contract approval – Sept. 2021
  • Construction – Oct. 2021

Budget

  • Estimated Cost: $200,000

Milestones

  • BOS approved budget for project – July 2021

Next Steps

  • Advertise project