Kingspoint

Drainage Channel Stabilization - July 2015
Scope of Work
This project consists of the correction of an erosion problem caused primarily by drainage from Southpoint Drive. The erosion is in a steep channel adjacent to environmentally sensitive areas with the potential to damage a residential structure. The correction of the problem will be through the use of a regenerative stormwater conveyance system that will not only stabilize the channel but will also treat the stormwater runoff.
Schedule
  • Civil Engineering Design - Complete - 100%
  • Construction Phase Begun - February 2015
  • Complete - April 20, 2015
Budget
  • Estimated Budget - $150,000
  • Williamsburg Environmental Group/Stantec - $43,903
  • Contract amount and percent completed - $42,852 - 97.6%
  • Additional services - $15,097
  • Centennial Contractors Enterprises, Inc. - $258,329
  • Contract amount and percent completed - $258,329 - 100%
Quick Links
Milestones
  • Preliminary design completed
  • Final design completed and approved
  • Easements obtained from all property owners involved to allow construction
  • Construction begun: February 23, 2015
  • Clearing complete
  • Work completed April 20, 2015
  • Punch list Items complete
Project Issues
  • Very small construction site with steep slopes and close proximity to a residential structure
  • Weather impacts due to snow and frequent rains